CBI Probe Sought Over Cost Jumps in Northern Railway Gati Shakti Works
Post-Award Tender Manipulation and Overlapping Contracts Exposed in Northern Railway’s Gati Shakti Unit; Whistleblowers Demand CBI Probe
Tender Twists and Unapproved Works Rock Railway Gati Shakti Unit Delhi Division
Questions Mount Over Northern Railway Gati Shakti Contracts
Red Flags Over Variations and Overlap in Gati Shakti Projects
Whistleblowers Flag Irregularities in Railway Gati Shakti Works
Audit Demands Grow Over Northern Railway Gati Shakti Variations
New Delhi: Serious allegations of financial irregularities, post-award tender manipulation, unapproved construction, and non-recovery of public funds have emerged within the Gati Shakti Unit (#GSU) of Northern Railway’s Delhi Division, with whistleblower inputs suggesting similar malpractices are widespread in the Lucknow unit (GSU LKO) as well. Official variation statements and public disclosures point to massive cost escalations, overlapping work scopes across multiple railway stations, and execution of works without duly approved drawings.
Massive Cost Escalations and Post-Award BOQ Changes
An examination of official “On Account Variation Statements” for two contracts awarded under the Amrit Bharat Station Scheme (#ABSS) in the Delhi Division reveals sweeping changes to the Bill of Quantities (#BOQ) after the contracts were awarded:
- Contract 1 (Agreement No. NR/DLI/GS/2023/0048): Awarded on October 13, 2023, to joint venture RSC-PCC-JV (#LOA No. 10445430088930) for platform shelters, concrete works, and balance Foot Over Bridge (FOB) works at Mansa, Narwana, Jind, Rohtak, and Bahadurgarh stations, the original agreement value of ₹32.97 crore (₹329,702,341.90) has surged through nine variations to ₹53.34 crore (₹533,397,940.19)—an overall increase of 61.78% (64.86% excluding special conditions). While Schedule B2 (worth ₹7.14 crore) was reduced by 100% to zero, Schedule A skyrocketed by 148.51% from ₹20.42 crore to ₹50.74 crore, and a new Schedule C worth ₹71.66 lakh was introduced. Individual line items saw extreme fluctuations, including a 4,364.29% jump in HSFG bolts, a 6,209.09% surge in suspended floor/roof shuttering, and a 1,035.27% increase in cement concrete works, alongside several original items being slashed to zero. Despite breaching the 50% variation threshold, balance works remain ongoing.
- Contract 2 (Agreement No. NR/DLI/GS/2026/0018): Awarded on May 22, 2026, to Bangkeshwar Singh-Siwan (LOA No. 01034190158181) for platform surfacing and FOB finishing works at Rohtak (ROK), Bahadurgarh (BGZ), Mansa (MSZ), Jind (JHI), Narwana (NRW), and other stations, the original Letter of Acceptance (LOA) value of ₹1.52 crore (₹15,197,462.25) jumped in its very first variation (Variation No. 1, approved in October 2026) to ₹2.20 crore (₹21,991,545.46), marking a 44.705% escalation. Specific items underwent drastic revisions: malba (debris) disposal surged by 900% (from 50 cum to 500 cum), 0.8 mm galvanized metal deck sheet work increased by 455% (from 100 sqm to 555 sqm), and 65,000 kg of Electric Resistance Welded (ERW) tubes (worth ₹90.31 lakh) were newly introduced for lift fabrication at Bahadurgarh, even as several originally tendered flooring, granite, and concrete pavement items were reduced by 100%.
These post-award modifications raise critical questions: Were the original BOQs drafted without proper site assessment, or were quantities deliberately altered after competitive bidding to confer undue financial advantage upon selected contractors?
Parallel Contracts and Overlapping Work Locations
Compounding concerns over tender integrity, both contracts cover identical railway stations—specifically Rohtak, Jind, Narwana, Mansa, and Bahadurgarh. While the 2023 contract covers platform shelters, RCC foundations, vacuum-dewatered concrete flooring, and 12-metre FOB balance works, the 2026 contract covers platform surfacing and FOB finishing works at the very same stations, including FOB deck slabs, lift cladding, and stair foundations at Bahadurgarh. Executing two separate contracts simultaneously at overlapping sites without clear scope demarcation risks duplicate expenditure, billing overlaps, and prolonged inconvenience to passengers.
Construction Without Approved Drawings and Allegations of Blackmail
Further irregularities were highlighted in an investigative thread on X by Railwhispers (@Railwhispers), which alleged that multiple Gati Shakti projects in Northern Railway are being executed solely on oral instructions, without duly signed drawings or mandatory approvals from competent authorities in the Drawing Registers. Even though station redevelopment works fall under the purview of the Central Vigilance Commission (CVC), the absence of verified drawings raises doubts about how much work was executed on the ground versus merely recorded on paper.

The thread also flagged reports that outsourced Project Site Supervision Agency (PSSA) staff in the Delhi Gati Shakti unit possess incriminating evidence of corruption and are allegedly using it to blackmail certain railway officials. Responding to these revelations, a whistleblower corroborated the findings, stating that the reports regarding the Gati Shakti Unit are entirely accurate and noting that similar large-scale irregularities are taking place in GSU Lucknow (LKO) without leaving a paper trail.
Non-Recovery of Negative PVC Dues
In addition to cost escalations, serious lapses have been flagged regarding the Price Variation Clause (#PVC) in older railway contracts. When PVC calculations yield a negative balance—meaning the contractor owes a refund to the Railways—concerned officials have allegedly failed to recover the amount from contractors. Withholding the recovery of legitimate government dues represents a direct loss to the public exchequer and points toward possible collusion and negligence.
Demands for Multi-Agency Investigation
Stakeholders and whistleblowers have called for immediate intervention by the Central Bureau of Investigation (#CBI), the Central Vigilance Commission (#CVC), and the Comptroller and Auditor General (#CAG) to conduct a comprehensive, independent audit of all the Gati Shakti Units work focusing specifically Delhi Division of Northern Railway. Key demands include:
- Scrutinizing the entire tendering process, original BOQs, post-award quantity variations, technical justifications, and scope overlaps between parallel contracts.
- Reconciling Measurement Books (MBs), Drawing Registers, approved drawings, and payment records alongside physical verification of on-site works.
- Investigating the non-recovery of negative PVC dues and the alleged blackmail involving outsourced PSSA staff.
- Fixing strict administrative and criminal accountability for officials responsible for manipulating competitive tenders and causing losses to the public exchequer. Contd.