RITES Inspection Lapses: Continued Non-Compliance in Kolkata ERO Spark Safety Concerns

KOLKATA: Fresh questions are being raised over quality assurance and compliance procedures within the Eastern Regional Office (#ERO) of #RITES Ltd., following revelations of recurring inspection lapses involving Kolkata-based vendor M/s Selvoc Engineering Company Pvt. Ltd.

Whistleblower reports and recent inspection documentation indicate that standard protocols mandated by railway specifications continue to be overlooked during third-party inspections (#TPI) for critical locomotive components destined for Chittaranjan Locomotive Works (#CLW).

The controversy follows an earlier exposé published on July 29, 2026, by #Railwhispers (“Railway Procurement Audit Reveals Severe Compliance Lapses In TPI Certification Procedure!”), which highlighted critical deviations in how RITES executed inspections by failing to adhere strictly to prescribed technical specifications.

Recurring Lapses in Recent Certificates

New evidence points toward similar procedural bypasses in subsequent inspections conducted by Inspecting Engineer #NitinKumar. Specifically, Inspection Certificate Nos. 2843564 and 1891564—both dated August 12, 2026 (referencing call details from July 2026)—were issued for Rotor Bars (Scheme-I Rotor, Drawing No. SKEL-4740 Alt-3, Specification No. RDSO/2008/EL/SPEC/0063/Rev-4) supplied by Selvoc Engineering Company.

Industry experts and railway monitors note that the persistence of these discrepancies raises urgent questions regarding whether such deviations are isolated incidents or have regrettably become standard operational practice within RITES’ Kolkata-based Eastern Regional Office and the vendor’s manufacturing ecosystem.

Call for Immediate Intervention

With thousands of critical components—such as the 7,260 rotor bars cleared under the recent certificates—cleared for supply to Chittaranjan Locomotive Works (CLW), stakeholders are demanding rigorous audits. The safety and reliability of electric locomotives depend heavily on uncompromising adherence to technical specifications and thorough quality checks.

Chittaranjan Locomotive Works and railway oversight bodies are now under pressure to intervene, verify the integrity of these inspection procedures, and clarify whether established compliance norms are being systematically compromised.

The inspection carried out by inspecting engineer #PalashDe doesn’t verify import of raw material as this import has to be done from only approved Sources as per QAP. Read—

Nov. 16, 2026: “Railway Procurement Audit Reveals Severe Compliance Lapses in Rites Certification Procedure!”