Historic Milestone: First Kavach Commissioning of WR in Vadodara Division
Mumbai: Vadodara Division, Western Railway has achieved a quantum leap in safety standards on 30 December, 2025 with the successful commissioning of the #Kavach System on the critical Bajwa-Ahmedabad (BJW-ADI) section, first in Western Railway.
Technical Snapshot of the Project
- Section: Bajwa to Ahmedabad (BJW-ADI)
- Station Kavach Make: HBL
- Route Length: 96 Kms
- Stations Covered: 17
Infrastructure
- Towers: 23
- Kavach Buildings/Huts: 20
- OFC Laid: 192 Km
- RFID Tags Installed: 2872
- Kavach Equipped Maiden Train: Sankalp Fast Passenger (59549/59550), ran with Loco WAP7 30459 equipped with HBL make loco kavach with 11 LHB coaches load.
- NMS installed at Division office, Pratapnagar and Ahmedabad.
Safety Impact
This system is now fully functional to automatically mitigate safety risks, ensuring-
- Prevention of consequences arising due to Signal Passed at Danger (#SPAD).
- Automatic Speed Control (Sectional speed, Loop lines & PSR supervision).
- Protection against Head-on and Rear-end collisions.
- SOS facility
- Automatic whistling at LC gates.