Yard remodelling work completed at Rourkela
The completion of yard remodelling work will ease congestion and facilitate the movement of passengers and goods trains
Kolkata, 16th October, 2023: To provide better service to the passengers, #Rourkela yard remodelling work was undertaken by South Eastern Railway (#SER) in connection with #construction of 3rd line between #Rourkela & #Bondamunda.
Yard remodelling commissioned with 393 route Electronic Interlocking having 135 #signals, 96 #points, 126 #Track Section along with bidirectional block working in 3 lines.
Yard modification involving 39 new #turnout and #conversion of 7 point to motor operation and #Automatic #Block_Signalling on UP/DN and 3rd line between Rourkela-Panposh has been commissioned on 15.10.2023.
Engineering works involved insertion of 39 new #Turnouts, 18 Turnout dismantling, about 2 km new track linking which includes 1 new line, 6 overrun lines machine siding and shunting neck. #OHE work included 180 nos. erection, OHE wiring of 15 nos. x-over/turnout, additional isolators, overhead wires removal etc.
The benefits:
- New full length line, L-11 will facilitate movement of all trains.
- Line no. 10 (short #CSL line) will be converted to full length line and will facilitate movement of all types of trains.
- Two additional passenger HL Platforms 6 & 7 will be operational at Rourkela very soon.
- Simultaneous reception and dispatch facility in both UP & DN grid with provision of individual overrun line for L-1 both side and L-2 in UP direction. It will felicitate faster train movement.
- Additional facility of L-11 both direction movement and L-8, L-9 & L-10 in DN direction movement.
- Auto signaling between Rourkela and Panposh for increasing sectional capacity.
- After completion of related NI work at Q, P, K, D & A Cabin of Bondamunda, existing UP & DN line will be converted to Jt. line (Bi-directional).
- OHE isolation between L-1, L-2 and L-3 for better maintenance and related facilities.
- New Rourkela Electronic Interlocking panel with latest facilities.
- Additional shunting neck facility at the Goods shed for faster placement and withdrawal of rakes.
The completion of #yard_remodelling work will ease congestion and facilitate the movement of passengers and goods trains.