The worst ever quality of Signalling work has exposed, the bad quality of work executed by the contractor

A serious #Safety related issue/input where #Public & #Passengers’ Safety involved is received today by #Railwhispers from #NFRailway, Maligaon, Guwahati.

Commissioner of Railway Safety (#CRS), North-East Frontier Circle, Kolkata was offered for #Inspection of Newly Constructed BG line from #Pawakhali (including) to #Thakurganj (excluding) in connection with #Arariya-#Galgalia (Thakurganj) New #BGLine project of #KatiharDivision of #NFRailway for Public Carriage of Goods and Passenger Traffic.

CRS observation and remark with photos taken on site regarding the worst ever quality of #Signalling work has exposed, the bad #quality of work executed by the signalling #contractor.

The #CRS observation states, “Various issues having direct bearing on #SAFETY and also #DEFICIENCY, indicating incompleteness of work were noted.” CRS has thankfully not issued the Authorization for operation of Passenger trains.

We investigated the matter and a copy of #LOA was obtained and found that the #signalling_contract was awarded to M/s #MRTSignalsLtd, Kolkata at a total cost of ₹74.67 crore.

Letter of Acceptance (#LOA) in favour of M/s MRT Signals Ltd. Kolkata

This serious matter is under #investigation in this multiple crore #scam in signalling work which has resulted in such bad quality life threatening situation and will be updated in next episode.

Sources say, M/s #MRTSignalsLimited, Kolkata is the same firm who had previously executed #Signalling work at #Bahanaga Bazar, #Balasore.

It is the hot topic of discussion at #NFRailway, Maligaon, at every level that situation of #Balasore has been created and repeated by the #signalling contractor.

The signalling #Contractor has NO mercy for the lives lost in the #Balasore-accident and #GMNFR/Construction is expected to initiate stern action against the culprit signalling firm, M/s #MRTSignalsLtd, Kolkata.

While #GMNFR/Construction has immediately removed #CSTE/Construction from the post and taking various action against the #Signalling officers and supervisors but NO action has so far been taken by the main culprit M/s #MRT Signals Limited, who caused such bad situation and has brought the dignity and image of Ministry of Railways and its officials to such lowest level.

Further investigation is being gathered and will be updated soon in next episode.